Pool Construction in Cabarete and Sosúa: What Changes the Price, How Long It Takes and Which Finish to Choose

Short answer: A concrete pool for a villa on the north coast usually takes us about 30 days to build once the permit and design are ready. There is no single price, because the cost depends on the size, the structure, the soil, the finish and the equipment. A plunge pool on flat ground and an infinity pool on a slope facing the sea are different projects. The way to get a real number is a quote with your lot and the size you have in mind.

Key takeaways

  • Typical build time: about 30 days for a pool (Saiz Solutions).
  • The price depends on dimensions, structure, soil, finish, edge type and equipment.
  • On the coast, plan for salt air and high groundwater from the design stage.
  • A pool can be built while the house is being finished, so it does not have to add time.

How long does it take to build a pool?

For a typical residential pool we plan about 30 days of work, from excavation to filling. That time can change with:

  • rain, which slows excavation and concrete work;
  • groundwater, which may need pumping during the excavation near the coast;
  • access, if machines and concrete trucks cannot reach the site;
  • the finish chosen, because some finishes need curing time.

On a new villa, the pool is usually built at the same time as the interior finishes, so it does not extend the overall schedule. See how long it takes to build a villa in Cabarete.

Concrete pool shell under construction next to a villa near Sosúa, before the finish is applied.

What changes the cost of a pool?

FactorWhat to know
Dimensions and depthVolume drives excavation, steel, concrete and finish area. A deep end adds more than its length suggests.
StructureReinforced concrete is the standard here. A pool built on a slope or partly above ground needs more structure and retaining walls.
Soil and groundwaterSand and high groundwater near the beach mean pumping during excavation and a careful design so the pool does not float when empty. Rock means harder digging.
Edge typeA standard edge is the simplest. An infinity (vanishing) edge needs a catch basin, more plumbing and very precise levels.
FinishPainted concrete, tile, or an aggregate finish such as Diamond Brite. Each has a different cost and lifespan.
EquipmentPump, filter, chlorine or salt system, lights, heat pump. Equipment near the sea needs protection from salt air.
Deck and surroundingsThe deck, coping, steps, shower and fence are often quoted with the pool. Ask.

That is why we quote each pool on its own. Send us the size and the lot and we will give you a number.

Which pool finish should you choose?

FinishProsWatch out for
Pool paintLowest initial cost; easy to renewNeeds repainting more often
Tile or mosaicDurable, many designsHigher cost; grout needs care
Aggregate finish (e.g. Diamond Brite)Hard, long-lasting surface with a natural look; resists stains and chemicals better than paintHigher cost than paint; needs a skilled applicator

We build new pools and also renew existing ones with paint or Diamond Brite. A pool that loses water, stains easily or feels rough is often a sign that the finish is at the end of its life. See our finishing and maintenance services.

What should you plan before you dig?

  1. Permit. A pool is part of the construction licence for a new house; on an existing house, check with the municipality. See construction permits in Puerto Plata.
  2. Setbacks. Respect the distances to property lines. On the coast, nothing can be built in the first 60 metres from the high-tide line, which is public land under Law 305 of 1968 (elCaribe).
  3. Rules of your community. Gated communities often have their own rules for works. See building in Sea Horse Ranch.
  4. Water source. Filling a pool takes a lot of water. Plan whether it comes from the network, a truck or your cistern. See water, power and septic.
  5. Power. Pumps run every day. Size them and plan for power cuts.
  6. Equipment location. Keep the pump room ventilated, dry and protected from salt air.
Finished pool in front of the sea at a villa on the north coast of the Dominican Republic.

Get a quote for your pool

We build and renovate pools in Cabarete, Sosúa and Puerto Plata. Send us the size you have in mind, a photo of the area and your location, or message us on WhatsApp.

FAQ

How long does it take to build a pool in the Dominican Republic?

For a typical residential pool, Saiz Solutions plans about 30 days of work once the design and permit are ready. Rain, groundwater and access can change it.

How much does a pool cost in Cabarete or Sosúa?

It depends on the dimensions, the structure, the soil, the edge type, the finish and the equipment. Each pool is quoted with the lot and the size in mind.

What is Diamond Brite?

Diamond Brite is a brand of aggregate pool finish made with quartz and cement. It is harder and lasts longer than paint, and is used both on new pools and to renew old ones.

Can a pool be built at the same time as the house?

Yes. On a new villa, the pool is usually built while the interior is being finished, so it does not add time to the schedule.

Can I build a pool close to the beach?

Not in the first 60 metres from the high-tide line, which is public land under Dominican law. Beyond that, the design must deal with sand and high groundwater.