Construction Permit in the Dominican Republic: What You Need Before Building in Puerto Plata

Short answer: To get a construction permit in the Dominican Republic you need the final land title and cadastral plan, a land-use certificate and no-objection letter from the municipality, an environmental authorization, and plans signed by CODIA-registered professionals. The application is filed online at the Ministry of Housing’s single window (VUC). For a non-complex project, the stated review time is up to 60 working days once the file is complete.

Key takeaways

  • The permit is issued by the Ministry of Housing, Habitat and Buildings (MIVHED) through the online Ventanilla Única de Construcción (VUC). The municipality (ayuntamiento) and the Ministry of Environment play their part first.
  • No final title and survey, no permit. Sort out the deslinde before you design.
  • Plans must be signed by professionals registered with CODIA.
  • Fees are mostly a percentage of the construction value, not a flat amount.
  • The licence is valid for one year. Plan to start within that time.

Permits are the part of a build that owners see least and worry about most. They are also the most common reason a project starts late. Here is how the process works for a home in Cabarete, Sosúa or Puerto Plata, and what you can do to avoid delays.

This guide summarizes public information available in October 2026. Requirements and fees change. Confirm the current list with MIVHED, your municipality and a lawyer before applying.

Who issues construction permits in the Dominican Republic?

Several institutions are involved, each with a role:

InstitutionRole
MIVHED (Ministerio de Vivienda, Hábitat y Edificaciones)Reviews the plans and issues the construction licence through the VUC
Ayuntamiento (municipality: Sosúa, Cabarete district, Puerto Plata)Land-use certificate, no-objection letter, stamps the plans, collects municipal fees
Ministry of Environment (Medio Ambiente)Environmental authorization
CODIAProfessional college of engineers and architects; its members sign the plans; collects its own fee
EDENORTE / water utilitySupply approvals for large projects

(inmobiliario.do, August 2026)

The ministry appears as MIVED or MIVHED in different sources; it is the same body after a name change.

What documents do you need for a construction permit?

For a private home, the core list is:

  1. Final property title (Certificado de Título) and the cadastral survey plan of the lot.
  2. Land-use certificate and no-objection letter from the municipality.
  3. Environmental authorization from the Ministry of Environment.
  4. Architectural, structural, electrical and sanitary plans, 24″ x 36″, stamped by the municipality and signed by CODIA-registered professionals.
  5. Project description, structural calculations and, where required, a geotechnical (soil) study.
  6. CODIA credential of the responsible professional.
  7. Photos of the lot.
  8. ID of the owner (cédula or passport) and, for companies, the commercial registry.

(inmobiliario.do, August 2026; elCaribe, June 2025)

Whether a soil study is required depends on the project and the lot; your engineer will tell you. Near the coast, with sand or high groundwater, it is often a good idea even when it is not mandatory.

What are the steps to get the permit?

  1. Prepare the lot documents. Title, cadastral plan and, if needed, the deslinde. This is where most delays start. See buying land to build in Cabarete.
  2. Design and sign the plans with CODIA professionals.
  3. Get the municipal certificates (land use, no objection) and the environmental authorization.
  4. Apply online at the VUC: create an account, fill in the form and upload each document as a PDF.
  5. Completeness check. MIVHED reviews that the file is complete and asks for corrections through the portal if something is missing.
  6. Initial fee and technical review: architecture, structure, electrical, sanitary, geotechnical and valuation.
  7. Lot inspection by MIVHED to confirm the current state of the site.
  8. Final payment and licence. MIVHED notifies you to collect the licence and the sealed plans.

(Steps as described by inmobiliario.do, August 2026.)

How much does a construction permit cost in the Dominican Republic?

According to the same source, the main fees are:

FeeAmount
Licence applicationRD$6,000
Municipal fee (arbitrios)2.5% of the construction value
CODIA fee2% of the construction value
MIVHED service fee0.1% of the appraised value, only above RD$6,000,000

(inmobiliario.do, August 2026)

In practice, the percentage-based fees are what matter: on a house, the municipal and CODIA fees together come to about 4.5% of the construction value as appraised. Add the professional fees for the plans and studies.

How long does a building permit take?

The published timelines, counted in working days from a complete file, are up to 60 working days for non-complex projects and up to 120 for complex ones (inmobiliario.do). MIVHED has also said it is working to answer complete applications within 30 days and issued 921 permits in the first half of 2026 (Dominican Today, July 2026).

Those clocks start after the municipal and environmental steps and only when nothing is missing. In Sosúa and Cabarete, the total time from starting the paperwork to holding the licence depends mostly on the lot documents: a lot with a clean title and its own survey moves much faster. Start the paperwork while the plans are being finished.

The licence is valid for one year from issue. If work does not start in that time, it has to be renewed.

Can you start work before the permit?

Not the construction itself. According to the same guide, MIVHED can authorize preliminary works (temporary installations, and excavation in some cases) and a partial start for non-complex projects in a few days, at no cost. Ask your builder whether this applies to your project before any machine enters the lot.

Building without a licence risks fines, stoppages and problems when you sell or insure the house.

Foundation work starting on a licensed residential project near Cabarete, Dominican Republic.

What causes permit delays on the north coast?

CauseHow to avoid it
Lot without final title or deslindeBuy individually titled land; start the deslinde early
Plans returned with observationsUse professionals who know the current regulations
Missing environmental authorizationStart it in parallel with the municipal certificates
Coastal or protected-zone questionsCheck the lot’s status before designing
Changing the design after submittingFreeze the design before applying

Do foreigners need anything extra?

No special permit is needed because you are a foreigner. The same process applies. What changes in practice is that many owners are abroad, so a lawyer with a power of attorney or the builder handles the visits and signatures. See building a house in the Dominican Republic from abroad.

Let us handle the paperwork

Saiz Solutions Builders is a family construction company based in Encuentro, Cabarete. We build homes, villas and pools in Cabarete, Sosúa and Puerto Plata. We handle the permits each project needs, so the owner does not have to deal with the offices. Plans and permits are quoted separately from construction.

Send us your lot details and we will tell you which documents you already have, which are missing, and how long the permit will take for your project. Or message us on WhatsApp.

Related: how to build a house in the Dominican Republic as a foreigner and how long a villa build takes.

FAQ

Who issues construction permits in the Dominican Republic?

The Ministry of Housing, Habitat and Buildings (MIVHED) issues the construction licence through its online single window (VUC), after the municipality issues the land-use and no-objection certificates and the Ministry of Environment gives its authorization.

How much does a building permit cost in the Dominican Republic?

According to an August 2026 guide, the application costs RD$6,000, plus 2.5% of the construction value for the municipality and 2% for CODIA, and a 0.1% MIVHED fee on projects appraised above RD$6 million. Confirm current fees with MIVHED.

How long does it take to get a construction permit?

Up to 60 working days for non-complex projects and 120 for complex ones, counted from a complete file, according to published guidance. Municipal and environmental steps come before that.

Do I need a permit to renovate my house?

It depends on the scope. Structural changes and extensions generally need a licence. Ask your builder and the municipality before starting.

How long is a construction licence valid?

One year from issue. If work does not start in that period, the licence must be renewed.